April 18, 2018

Spring is here and the new building at Spring Valley Village is steadily approaching completion! Installation of the exterior brick is complete, and windows have been added to the second floor. 

In addition to delivering more space for exciting new retailers, we'll be r...

March 8, 2018

This week, brick will be laid along the exterior walls of the building. You can see the team’s progress in the photo above!

Additionally, Capital One’s exterior ATM will be inaccessible due to construction activity, starting today. An ATM has been set up inside of the b...

February 12, 2018

Announcing the newest arrival at Spring Valley Village – Pizzeria Paradiso! Scheduled to open in the fall of 2018, this location will be the fifth restaurant for the local pizza chain. Pizzeria Paradiso puts a contemporary spin on the classic “pizza & beer combination”...

February 6, 2018

This week installation of a duct bank along the sidewalk on Massachusetts Avenue began, and is expected to finish up by the end of the week. As we move closer to project completion, light construction activity may occur on Saturdays in addition to regular construction...

January 18, 2018

Progress at Spring Valley Village is coming along nicely! Take a look at the "Then and Now" photos above! 

The team will be on site during normal hours this week. Be sure to check back for important updates on construction and leasing in the coming weeks! 

January 5, 2018

We are pleased to announce the newest addition to Spring Valley Village – Compass Coffee! Voted D.C.’s Best Coffee Roaster by Washington Post readers, Compass Coffee is a local business founded by two Marines Corps veterans in 2014. We are eager to welcome them to the...

December 20, 2017

Happy holidays! Construction will continue through the holiday week. Backfill stone at the subgrade and steel column placement with both be complete by this Friday, December 22nd. The forming and pouring of the first floor concrete slab will occur during the following...

December 7, 2017

The construction team made great progress this week! Check out our Gallery page for a full time-lapse video of the project! Construction will occur during regular working hours next week. 

November 30, 2017

Structural steel installation is well underway at Spring Valley Village!  The construction team will be on site from 7:00AM-4:00PM, Monday through Friday next week. A mobile crane will be positioned in the parking lot for approximately four weeks as the team installs t...

November 20, 2017

This week, construction activity will be limited due to the Thanksgiving holiday. The team will focus on completing the elevator and stairwell shaft walls at the basement level. Additionally, the CMU stem walls, which connect the foundation of the building to the verti...