Construction Update - December 20th

December 20, 2017

 

Happy holidays! Construction will continue through the holiday week. Backfill stone at the subgrade and steel column placement with both be complete by this Friday, December 22nd. The forming and pouring of the first floor concrete slab will occur during the following week.

 

Both a concrete and a pump truck will be onsite over the next two weeks, but will remain stationed within the confines of the construction fencing. We hope that everyone has a safe and enjoyable holiday!